COLUMBUS STAINLESS STEEL, AFRICA
- webadmin
- Latest News
THE CHALLENGE
PROXA was tasked with managing both the effluent water volumes and excess salt on a major steel mill, while meeting budget constraints. What’s more, the client required a Zero Liquid Discharge (ZLD) plant in order to avoid any future liabilities and meet environmental legislative requirements.
OUR SOLUTION
PROXA committed to working with the commissioning client to value-engineer a project execution philosophy that would meet Columbus Steel’s long term objectives, while being mindful of their short term budget constraints.
As such, PROXA executed the project in 3 phases:
- The first phase included the design, supply, installation and commissioning of a forced circulation evaporator designed with 2 heating legs. This enabled Columbus to initially install 50% of the heating capacity, while the vapour body was designed for the full future load.
- The second leg was installed a few years later once capacity on site increased and additional funds became available. To maintain performance of the evaporator a small purge was required, which was temporarily stored on site.
- The third phase included the design and installation of a small purge crystalliser, treating the remaining purge and meeting the client’s objectives of achieving a ZLD plant.
HOW PROXA ADDED VALUE
Our flexible approach to design and value engineering enabled us to meet both long term objectives and short term site budgetary constraints. We also achieved energy efficiency through the use of 2 sets of 2-stage mechanical vapour recompression fans. And, before the client committed to the full scale plant, the process for the purge crystalliser was developed on bench scale and piloted. What’s more, we implemented a unique process generating 2 solid and 2 liquid products, all of which offered value to the customer. In short, a true ZLD plant. We also attained plant longevity through the use of high grade materials such as stainless steel 904L and titanium grade 2 and 12. The purge crystalliser was manufactured in a variety of materials such as Avesta 254SMO, FRP, titanium and carbon steel.
FEED WATER
Pickle liquors from a stainless steel production process containing HF, HNO3, SO4 and some Cl
The main cation is Fe, with some H and Na
PRODUCT WATER
The primary effluent treatment yields iron hydroxide precipitates, containing calcium fluoride.
The products of the ZLD crystalliser include:
Calcium sulphate cake – for resale to local farmers
Sodium nitrate crystals – for resale to the explosives industry
Calcium nitrate solution – for resale to the fertiliser market
Clean process condensate – to be recycled within the mill.
PERFORMANCE TARGET
96 000 kg/hr water evaporation after expansion to 4 fans.
PROCESS
Solution pre-treatment
Forced circulation evaporator
2-Stage mechanical vapour recompression fans
Double effect forced circulation crystalliser
Filter press for removal of calcium sulphate
Cooling crystalliser for sodium nitrate
Centrifuge to remove sodium nitrate
Maturation tanks for storage and post precipitation of calcium sulphate
PROCESS RELIABILITY
The plant has been in continuous operation since 2004 and is meeting all client’s key performance objectives.
Client: Columbus Stainless Steel
Refer to this page to see all of our water treatment services.